буржуйский "наш ответ Чемберлену" на первую часть вопроса:
+++
Date Deployed
deliveries beginning in 2002
operational by 2004 ...
+++
на вторую часть:
Low rate production is scheduled to begin in FY99. The aircraft production rate will gradually increase to 36 aircraft per year in FY 2004, and will continue that rate until all 339 aircraft have been built (projected to be complete in 2013). Initial Operational Capability of one operational squadron is slated for December 2005.